Nepal’s Power Sector Milestone: Chilime-Trishuli Transmission Line Completed

Nepal's Power Sector Milestone
Share It On:

4th November 2024, Kathmandu

The Chilime–Trishuli 220 kV transmission line, constructed to transmit electricity from hydroelectric projects along the Trishuli River and its tributaries into the national grid, has been completed.

Nepal’s Power Sector Milestone 2024

The transmission line stretches 28 kilometers from the Chilime Hub substation in Thambuchet, Amachodingmo Rural Municipality in Rasuwa, to the Trishuli Three B Hub substation in Kispang Rural Municipality, Nuwakot.

Despite challenging terrain and a tight timeline, including national holiday periods during Dashain and Tihar, employees and contractors worked around the clock to complete the project, as stated by Kulman Ghising, Executive Director of Nepal Electricity Authority (NEA). He noted that this transmission infrastructure was essential for the power generated by 111 MW Rasuwagadhi and 42.5 MW Sanjen, among other hydroelectric projects in Rasuwa, to reach the national grid.

Building the transmission line in geographically demanding and hazardous mountainous areas required tremendous efforts, including transporting materials such as stones, sand, tower components, and water via mules or by hand due to the lack of access roads, steep cliffs, and landslide-prone zones. Despite these challenges, the team completed the line, marking a significant achievement for Nepal’s energy sector. The project faced delays due to adverse weather, land use complications in forested areas, COVID-19 disruptions, and local resistance. The NEA is now moving forward with plans for the Chilime–Kerung cross-border transmission line, designed to enable power trade with neighboring China.

As part of the Chilime–Trishuli 220 kV project, the Chilime Hub and Trishuli Three B Hub substations (rated at 220/132/33 kV) have also been constructed. Power from Trishuli Three B Hub will now feed into the Trishuli–Kathmandu 220 kV line, integrating with the national grid at Matatirtha, Kathmandu. Meanwhile, electricity generated by the Sanjen and Rasuwagadhi projects will reach the Chilime Hub and be routed through the Chilime–Trishuli line into the national network.

A total of 76 towers have been built along the 28-kilometer line, covering altitudes from 680 to 2,600 meters above sea level. Thirty-three of these towers were erected in areas without road access, necessitating the construction of 20 kilometers of new access roads by the NEA’s High-Voltage Grid Department. Construction materials were transported manually and by mule, with helicopters assisting in the installation of two specific towers.

One segment of the line, spanning 1,235 meters from Tiruvillage to Siruchet in Uttargaya Rural Municipality, was completed using drone technology for wire stringing across the Mailungkhola gorge. The Chilime–Mailung segment consists of a 20-kilometer double-circuit line, while the Mailung–Trishuli Three B Hub segment spans 8 kilometers in a multi-circuit configuration. This multi-circuit line is intended to integrate the 216 MW Upper Trishuli–1 hydroelectric project, which is led by Korean companies. The Upper Trishuli–1 project will cover 60% of the costs associated with the multi-circuit line.

The estimated cost of the Chilime–Trishuli project is USD 362.89 million, financed by the Government of Nepal and the NEA with grants from the German Development Bank (KfW) and concessional loans from the European Investment Bank (EIB), an institution established by the European Union.

In 2017, NEA awarded the contract for transmission line and substation construction to China’s Pinggao Group, with implementation beginning in December 2017. The completion of this project is expected to significantly enhance Nepal’s power transmission capacity and help drive economic growth by facilitating uninterrupted power supply across regions.

Key Highlights:

Project Length: 28 kilometers
Transmission Capacity: 220 kV
Total Towers: 76
Altitude Range: 680 to 2,600 meters
Cost: USD 362.89 million
Completion Date: October 2024

For more: Nepal’s Power Sector Milestone


Share It On:

Recent Posts

Hero MotoCorp Xtreme Series 2024: Xtreme 125 R & 160 R Launch in Nepal

Hero MotoCorp Xtreme Series 2024: Xtreme 125 R & 160

Share It On:11th December 2024, Kathmandu  Hero MotoCorp, one of the most trusted and admired names in Nepal’s two-wheeler industry,

FNCCI Leadership Election Reforms 2024: Direct Elections & Gender Equality in Nepal’s Business Sector

FNCCI Leadership Election Reforms 2024: Direct Elections & Gender Equality

Share It On:11th December 2024, Kathmandu In a groundbreaking decision, the Federation of Nepalese Chambers of Commerce and Industry (FNCCI)

Google Unveils Willow Quantum Chip: Solving Supercomputer Problems in Minutes

Google Unveils Willow Quantum Chip: Solving Supercomputer Problems in Minutes

Share It On:11th December 2024, Kathmandu Google has unveiled its new quantum chip, Willow. This chip can solve problems that

Nabil Bank’s SSE Fellowship: Empowering Social Entrepreneurs in Nepal

Nabil Bank’s SSE Fellowship: Empowering Social Entrepreneurs in Nepal

Share It On:11th December 2024, Kathmandu Nabil Bank has started the fourth batch of its Nabil School of Social Entrepreneurship

Yamaha Nepal Sales Skills Contest: Celebrating Excellence in Kathmandu

Yamaha Nepal Sales Skills Contest: Celebrating Excellence in Kathmandu

Share It On:11th December 2024, Kathmandu Yamaha Nepal successfully organized its Regional Sales Skills Contest in Kathmandu on 9th December

Barsha Basnet Wins 125cc Scooter Dirt Race at TVS Motosoul 2024

Barsha Basnet Wins 125cc Scooter Dirt Race at TVS Motosoul

Share It On:11th December 2024, Kathmandu Marking a historic achievement for Nepal’s motorsport scene, Barsha Basnet has clinched the title